Policy & Governance

Victoria Infrastructure Hearing: Target Cost Raised by A$6 Million, Contractors Reap About A$2 Million in Additional Profit

According to ABC News Australia, the first public hearing of Victoria's Royal Commission into the Integrity of Major Public and Civil Infrastructure Projects focused on the Gap Road level-crossing removal project in Sunbury. After the target cost was raised from A$110 million to A$116 million, Rail Network Alliance delivered the project for A$104 million and secured about A$2 million in additional profit through a savings-sharing mechanism. The hearing heard that the state government initially p

0 viewsSign in to save
TRUTH ERA

ABC News Australia reported that the first public hearing of Victoria's Royal Commission into the Integrity of Major Public and Civil Infrastructure Projects revealed a cost arrangement under scrutiny: after the government raised the project's target cost, the contractor alliance nevertheless secured about A$2 million in additional profit through "savings-sharing".

The opening hearing focused on the Gap Road level-crossing removal project in Sunbury, north of Melbourne. The project's original target cost was A$110 million, but it was raised to A$116 million after work stopped in June 2022. Rail Network Alliance, including John Holland and CPB Contractors, ultimately delivered the project for A$104 million. The final cost was below both the original and revised targets. The resulting controversy is that changing the benchmark altered the calculations used to share overruns and savings.

Chris Young KC, counsel assisting the Royal Commission, told the commission that when actual costs exceeded the government's target, contractors bore half of the overrun up to an agreed cap, while the state government covered costs above that cap. When actual costs came in below target, contractors could receive 35% of the savings. He said: "As it happened, every dollar spent on Gap Road was initially paid by the state government."

The arrangement created an asymmetry between rewards and risks: the state government paid upfront; contractors bore only part of any overrun up to the cap and shared in the savings when delivery came in under target; costs above the overrun-sharing cap remained the responsibility of the state budget. The target cost was therefore not merely a budget benchmark, but also determined who bore the risk of overruns and how savings could be converted into profit. By accepting a higher target, the government both raised the threshold at which contractors began sharing overruns and increased the amount of savings available for distribution.

According to ABC's reporting on the hearing records, CFMEU officials repeatedly stopped work over safety concerns on 6 and 7 June 2022. Citing documents, Young said no corrective measures had been taken on site in response to safety notices between 3:11 p.m. and the resumption of work at 6 p.m. that day, although the documents appeared to show that the parties had agreed to meet the CFMEU's requirements. After the stoppage, the number of workers provided on site by temporary labour company B K Labour Hire rose from two to 20, and the company had billed contractors A$1.2 million by September that year. Traffic management company CCL also charged 85% more than the provider previously used. These materials show that staffing and cost arrangements changed rapidly after the stoppage, but the figures alone cannot establish a direct causal relationship between the target-cost increase, the stoppage and all additional costs.

The hearing also read into the record a 2017 internal memo from John Holland. The memo said the CFMEU had "unprecedented access" to ministers and other key Victorian government stakeholders, and anticipated that the union might possess substantial information about proposed tenders and offer input into the tender process. Victorian Premier Ben Carroll said he did not know the CFMEU had such access. The memo reflected John Holland's internal assessment at the time and cannot, by itself, prove that the government broke the law or that the union actually influenced the tender process. It did, however, place a potential conflict of interest before the investigators: if such access might have allowed the union to obtain information about tenders in advance, how would contractors compete if they expected such access to exist?

The Royal Commission said it had received similar incident statements involving several Victorian public infrastructure projects, including North East Link, while noting that some government agencies had not submitted documents as required or within the prescribed deadlines. This made it necessary to pursue the relevant practices across projects, but the existing material is insufficient to confirm that the same arrangements existed elsewhere or to calculate the overall scale of the losses.

Outside the hearing, lawyer Geoffrey Watson SC told ABC that the investigation was not only aimed at the union, but also at the top-tier contractors profiting from the system. In this case, the central issue was the contractual incentives between the government and contractors: the state government paid upfront, contractors shared in the savings, and overruns beyond the sharing cap remained with the state budget. The CFMEU's conduct in relation to work stoppages, safety remediation and site access still has to be tested against the allegations. But the questions of who approved the target-cost increase, who verified the final cost and how contractors obtained additional profit must not be allowed to recede into the background merely because the investigation is focusing on the union.

The commission said the lines of inquiry raised at the start of this round were allegations at this stage, some of which had been denied, and could not be treated as final factual findings. Further public hearings will summon witnesses and examine organised crime, the allocation of government funds and project selection. Key questions outstanding include who approved the increase in the target cost to A$116 million, who verified the final delivery cost of A$104 million, and whether the missing documents can demonstrate that the same profit mechanism was extended to North East Link and other major projects.